Relationship between work and time

Comprehensive study of Work and Time relationship for CBSE Class 11 Applied Mathematics, covering unit work method, efficiency, and collaborative tasks with step-by-step solutions.

The Concept of Unit Work

In work and time problems, the total work is often assumed to be 1 unit. If a person can complete a piece of work in 'n' days, their rate of work (work done in 1 day) is represented as 1/n. This implies that work and time are inversely proportional; as the time taken increases, the efficiency or rate of work decreases.

Rate of work = 1 / Time taken to complete the work
Example 1: If A can complete a task in 10 days and B can complete the same task in 15 days, how long will they take to complete it working together?
Show Step-by-Step Solution

• Calculate A's 1-day work: 1/10.
• Calculate B's 1-day work: 1/15.
• Calculate combined 1-day work: 1/10 + 1/15 = (3+2)/30 = 5/30 = 1/6.
• Find the total time taken by taking the reciprocal of the combined work: 6 days.

Answer: They will complete the work in 6 days.

Efficiency and Work Relationship

Efficiency is defined as the work done by a person in unit time. If Person A is twice as efficient as Person B, then Person A will take half the time compared to Person B to complete the same task. The relationship can be expressed as: Work = Efficiency × Time.

Efficiency A / Efficiency B = Time B / Time A
Example 1: P is twice as efficient as Q. If Q can finish a project in 20 days, how long will P take?
Show Step-by-Step Solution

• Identify the ratio of efficiency: Efficiency(P) = 2 * Efficiency(Q).
• Use inverse proportionality: Time(P) = Time(Q) / 2.
• Calculate: 20 / 2 = 10.

Answer: P will take 10 days to finish the project.